|
Day |
2010 |
When it started! |
4th Sept
then again 26th Dec |
|
1 |
4 Sept 2010 |
7.1 Magnitude
4:35am |
You Rocked our World "WOW" we
had never experienced anything like this in our lives -
Brookhaven was blessed this time, but we all suffered lots of
breakages etc |
|
114 |
26 Dec 2010 |
4.9 Magnitude
10:30 am |
Centred under
the city centre this caused more damage than was first thought
to many building that eventually collapsed on 22nd Feb 2011. |
|
|
2011 |
YEAR 1 |
22nd Feb, 13
June, 23 Dec |
|
172
1 |
22 Feb 2011 |
6.3 Magnitude
12:51 pm |
|
This hit us hard! |
|
 |
| |
- liquefaction,
- flooding,
- no power,
- no water,
- no sewer,
- no phones,
- impassible streets
|
|
- Brookhaven will never be
the same again! |
|
|
4 |
25 Feb 2011 |
Power Back |
Nice to turn
on TV and see what was happening, with street impassable and my
radio broken |
|
14 |
7 March 2011 |
Roof |
Roof repairs made $3,000 - EQC
would not pay it was over $2,000 but later re-imburse |
|
14 |
7 March 2011 |
Water Back |
At last water back for some of us |
|
54 |
16 Apr 2011 |
5.3 Magnitude |
|
|
64 |
26 Apr 2011 |
Doors |
Finally have
some internal doors working again - necessary with winter
approaching |
|
80 |
12 May 2012 |
EQC Inspection |
1.30 to 4:30 pm |
|
112 |
13 June 2011 |
5.5 Magnitude
1:00 pm
6.4 Magnitude
2:20 pm |
Two big ones today
-
More liquefaction, flooding,
-
no
water,
-
large sink holes in road again
|
|
118 |
19 Jun 2011 |
Water Back |
|
|
121 |
22 Jun 2011 |
Orange Zone |
Because of damage as a direct
result of the magnitude 5.6 and 6.3 earthquakes which struck on
13 June, Brookhaven and many other areas were put in the
ORANGE ZONE
until adequate assessment of land could be obtained. |
|
133 |
4 Jul 2011 |
Arrow |
House
Assessment |
|
154 |
25 Jul 2011 |
Now its Snowing |
As
if there earthquakes are not enough
now we wake to a thick blanket of
snow,
can see any of the potholes and
that makes driving difficult.
Even need gumboots to get to
portaloo on the traffic island! |
|
167 |
Early Aug 2011 |
Sewer Back |
For some of us
this is quite a relief! |
|
175 |
15 Aug 2011 |
2nd Snow Fall |
- Two snowfalls in one year.
- Polar blast brings chaos to
Christchurch
- most stay home,
- little is open |
|
246 |
25 Oct 2011 |
AMI |
Letter from AMI we
are deemed Repairable |
|
249 |
28 Oct 2011 |
Green Zone
TC3 |
Many were shocked to hear, after being told Brookhaven had an
area wide problem and expecting to go red, and then to be
reclassified
GREEN ZONE
in
BLUE TC3
category |
|
259 |
7 Nov 2011 |
FBRA Meeting |
Ferrymead Brookhaven
Residents Assn meeting held at Samoan Church hall in Woolston
6:00pm |
|
266 |
14 Nov 2011 |
CERA Meeting |
Woolston
Working Men's Club 6:00-8:00 pm |
|
267 |
15 Nov 2011 |
AMI |
House now Rebuild -
because of the land |
|
269 |
17 Nov 2011 |
CERA Meeting |
Woolston
Working Men's Club 11:00-1:00 pm |
|
305 |
23 Dec 2011 |
6.0 Magnitude
3:18 pm |
Just as things are winding down
for Christmas - here we go again! With most on Christmas
break we were given little info but there was even more damage
sustain, and that is just coming to light a month on........ |
|
|
2012 |
YEAR 2 |
2nd Jan then
the assessments start |
|
315 |
2 Jan 2012 |
5.5 Magnitude
5.45 am |
It is now 2012
and quakes have not finished with us yet |
|
319 |
6 Jan 2012 |
Seismic Briefing |
GNS Science and Tonkin and
Taylor addressed closed meeting a good summary can be found
here |
329
345 |
16 Jan -
1 Feb 12 |
Waste Water |
Stronger Christchurch is flushing and checking all pipes in
Brookhaven area to ascertain the state of the infrastructure in
the area |
|
339 |
26 Jan 2012 |
Land
Assessments |
EQC Land
assessments complete, reports coming by April
Source |
|
344 |
31 Jan 2012 |
Community
Meeting |
Community Meeting for Ferrymead Brookhaven
Residents with CERA/EQC/AMI/IAG/CCC
Summary |
| 347 |
3 Feb
2012 |
GeoTech TC3
Land |
TC3 properties GeoTech work on
foundations assessment to start in March
Source |
|
1 |
8 Feb 2012 |
AMI - Arrow |
Settlement
agreement To Rebuild - Decision for demolishing and
rebuild on same site is possible - signed |
|
8 |
15 Feb 2012 |
Arrow/Golden Homes |
Start building plans
subject to GeoTech, surveyors report and flood levels being
determined. |
|
27 |
5 Mar 2012 |
Arrow/Golden Homes |
Further
meeting |
|
29 |
7 Mar 2012 |
Arrow |
Site inspection regarding
retaining some landscaping |
|
58 |
5 Apr 2012 |
AMI to SR |
AMI was sold
to IAG so all claims now handled by Southern Response (SR) |
|
79 |
26 Apr 2012 |
Geo Tech |
Still weeks away |
|
81 |
28 Apr 2012 |
DBH Foundation guides |
TC3 Foundation Guides released today |
|
104 |
21 May 2012 |
Variation 48 |
They need to determine if
section is above flood level |
|
136 |
22 Jun 2012 |
GeoTech-Pro Drill |
Core sample
taken through concrete drive to 16 metres deep all sand. |
|
149 |
5 Jul 2012 |
Endorsement |
AMI (SR) Files sent for
agreement with EQC this is holding up further progress |
|
154 |
Jul 2012 |
Geo Tech Report |
Report sent
for final review |
|
157 |
13 July 2012 |
Southern Response |
Confirmation to SR that we agree
with EQC that100% claim was 22 Feb Quake |
|
209 |
3 Sept 2012 |
Geo Tech Report |
Still awaiting final review |
|
220 |
2012 |
YouTube |
Earthquake Recovery CRAP a nice little
summary
http://www.youtube.com/watch?v=r-fu3Ec0Geo |
|
223 |
17 Sept 2012 |
Project Manager |
Request for new PM
refused |
|
255 |
19 Oct 2012 |
Geo Tech Report |
Still awaiting final review |
|
276 |
9 Nov 2012 |
Geo Tech Report |
Still awaiting final review |
|
|
2013 |
YEAR 3 |
A year of
waiting |
|
364 |
5 Feb 2013 |
Geo Tech Report |
Finally
released. |
|
366 |
7 Feb 2013 |
Foundations |
We were informed - wooden floor
with detached garage - we challenged this decision |
|
367 |
8 Feb 2013 |
Change decision |
We are now allowed “Firth Re-levellable concrete floors”, which
is a concrete slab and a rib raft.
|
|
400 |
13 Mar 2013 |
Shallow Geo Tech |
This is necessary to
determine design of concrete slab |
|
409 |
22 Mar 2013 |
Meeting Arrow/Builder |
Curve ball
from this meeting was a change of rules choices now -
Replicate or Build to Budget. This after being told by Arrow
the we would need to eliminate the hips in roof and opt for a
simpler design as well as choose light weight materials, no
brick or concrete tiles as we currently have. |
|
422 |
4 April 2013 |
Golden Homes |
Costing received for
"Replicate" - Also requested "Build to Budget"
price.
Southern Response initially agreed we could change 1 internal
wall using the same footprint - then they changed the rules. The
Build to Budget plan we submitted same square metres, L shape
(removing most of hips in roof) and putting all plumbing on one
side of house. Arrow suggesting we had to have polystyrene
cladding the builder refusing to build with it, we don't want
it! |
|
438 |
April 2013 |
EQC Land Assessment |
Only minor
land damaged noted |
|
453 |
5 May 2013 |
Replicate Decision |
Documents signed to
Replicate
- we were then informed we could make NO changes - not
even a light switch. Build to Budget price was received
and legal advice sort - both came in at same price, so Build to
Budget option plans submitted. |
|
457 |
9 May 2013 |
Change to B to B |
On the basis that the Build to
Budget has come in at the same price as the replicate |
|
461 |
13 May 2013 |
Signed off |
Plans were signed off today -
told expect 5 working days |
|
461 |
13 May 2013 |
EQC Land Results |
Land damage
less that minimum excess - no payout |
|
476 |
28 May 2013 |
Firth Engineers |
12 days still no plan
confirmation! Now they can't proceed until Firth Engineers
decide if they can design a foundation for our plan. That
decision we are told is weeks away! Will we get the plan we
submitted or will we have to start again? |
|
497 |
18 June 2013 |
Foundations |
Arrow are
insisting on Firth Foundations builder want to use their own -
result arrow foundation - builder above ground. |
|
505 |
26 June 2013 |
Ombudsman |
Lack of progress considering
taking case to Insurance Ombudsman |
|
516 |
7 July 2013 |
Plans |
Plan
simplified removing hips from roof and putting plumbing to one
side - likely to be more acceptable for consent. |
|
525 |
16 July 2013 |
Meeting SR Arrow |
Oh the rules have
changed yet again (the goal posts have moved) we can no longer
Replicate - because we have a brick house and brick is not
longer allowed on TC3 land.
With legal advice it became necessary to sign a new
(second) MOU this time agreeing to Build to Budget, with
SR/Arrow costing our DRA and builder submitting price for
simplified house plan removing the hips in roof and making plan
L-shaped within same sq metres. |
|
542 |
2 Aug 2013 |
Southern Response |
Supply new
figures for DRA giving us a Build to Budget price |
|
545 |
5 Aug 2013 |
Golden Homes |
Require details of Window Glass
current film cannot put on new double glazing as it would void
warranty |
|
553 |
13 Aug 2013 |
Golden Homes |
Supply figures
for Build to Budget - $12,000 difference with DRA |
|
556 |
16 Aug 2013 |
Golden Homes |
Minor changes needed in plans
expected back in one week - still not back |
|
562 |
22 Aug 2013 |
Southern Response |
Requesting me
supply Golden Homes pricing when it has already been sent to
Arrow - because of a rule change the Project Manager has not
opened it. |
|
571 |
31 Aug 2013 |
Golden Homes |
Going back to Arrow for
clarification on some points |
|
575 |
4 Sep 2013 |
Arrow International |
Still waiting
on confirmation from QS |
|
|
|
WE WAIT |
 |
Residents still suffering from 'quake-brain'
GREY
MATTERS: Quake-brain has got worse for many as the
earthquake recovery reaches its third year.
Article
in "The Press"
by John McCrone
14 September 2013
Click Here
The
stresses of living, the waiting, the rule changes, the
processes, the delays, lack of answers, how do you move
forward, life on hold for nearly 3 years now! |
|
|
594 |
23 Sep 2013 |
Arrow International |
Prices yet to be
agreed - we need to WAIT for a Project Manager to be
appointed
(thought we already had one! Oh No! Rules
changed again!) |
|
595 |
24 Sep 2012 |
Southern Response |
Email Case
Manager - Automated Response saying she has left - sent email to
address provided no response. Wait 3 days |
|
597 |
26 Sep 2013 |
Southern Response |
Ring - call put through to
Settlements - advised now rebuild team and repair them -
Repair Team failed to return my call - it would appear we
have no Case Manger for now!!! |
|
598 |
27 Sep 2013 |
Southern Response |
Finally spoke
to Rebuild Team manager who gave me name of a new case manager.
The case manager then gave me name of a new Arrow Project
Manager. - Another step forward we hope! |
|
609 |
8 Oct 2013 |
Southern Response/Arrow
POSTPONED |
Meet new Case manager and new
Project Manager with view to handing over project from Southern
Response to Arrow for rebuild. Arrow could not make it!!! |
|
610 |
9 Oct 2013 |
|
With work
being reassigned in Arrow the communication with Golden Homes is
non existent at present - can this be sorted before the
rescheduled meeting so things can move forward! |
|
616 |
15 Oct 2013 |
Arrow International |
Finally we get to meet our new
Project Manager ahead of our meeting, he visited the property to
get an understanding of our situation. |
|
618 |
17 Oct 2013 |
Southern Response/Arrow
RESCHEDULED |
So we met our
new Case Manager and the Project Manager but the builder failed
to supply the necessary details for us to confirm figures and
proceed. We were advised to contact SR Temporary Accommodation
Team to start the process for accommodation, we were given a
choice of removal and storage contractors to start getting
quotes, we were told to get in touch with EQC re carpets and
drapes. Yet still no confirmed way forward. |
|
619 |
18 0ct 2013 |
Accommodation |
We have been offered 2 bedroom
townhouse with flexible start date probably Feb/Mar for 6 months
- it is such a relief! |
|
625 |
24 Oct 2013 |
AMI Insurance |
We receive a
bill from AMI for our house insurance - we have just been told
by SR our house is a right off - how do you insure something
that is of no value? We are told the premium has been
discounted because there is a claim against the property, that
we need to pay in full and once demolition certificate is issued
balance of premium will be refunded. |
|
626 |
25 Oct 2013 |
WE WAIT |
A week on and still NOTHING - no
word from builders or project manager, how long before we get
to next step?? |
|
630 |
29 Oct 2013 |
Golden Homes |
Past Labour
Weekend now, still nothing - try to contact project manager no
reply, went to visit builder who told us he had been waiting
since August for B2B (Build to Budget) figures from Arrow to
enable him to proceed |
|
631 |
30 Oct 2013 |
|
Sent email to all parties - we
are assured that that figures will be sent from Arrow to
Builder TODAY - this is not our job we are client, but
if we do nothing it just drags on! |
|
632 |
31 Oct 2013 |
Arrow International |
Turns out
Arrow don't have the figure and are still waiting on Q S and
that dates back to 2nd August - 3 months to update B2B
figures!!!!! |
|
633 |
1 Nov 2013 |
WE WAIT |
We were promised updated figures
would be sent to builder by today and we would be informed -
but nothing! |
|
636 |
4 Nov 2013 |
Legal Advice |
On legal
advice we requested access to files from Southern Response under
the terms of the Privacy Act |
|
637 |
5 Nov 2013 |
Arrow International |
Updated figures for B2B now back
from QS being sent to Southern Response for sign off. |
|
639 |
7 Nov 2013 |
Southern Response |
Email say
figures will not be available until Mon or Tue because our file
is with administration |
|
643 |
11 Nov 2013 |
Southern Response |
Figures have been emailed today
- but builder still does not have a copy. |
|
646 |
14 Nov 2013 |
Golden Homes |
Builder
confirmed documents received - says they will have an answer by
Mon 18th |
|
651 |
19 Nov 2013 |
|
We asked "Is the
figure given sufficient to build our house?" the reply well we
are still waiting................. |
|
658 |
26 Nov 2013 |
WE WAIT |
Who is holding
us up, is it Southern Response, Arrow or Golden Homes or a
combination of all 3?
Would changing builder help? What can we do to move things
forward - we just want to get on with it? |
|
661 |
29 Nov 2013 |
Golden Homes |
Failed to deliver in 48
hr deadline with updated pricing - its now 72 hours and no one
at company can be reached!! |
|
667 |
Now |
it's December |
Still waiting
- now 7 working days later - can you feel the frustration!! |
|
|
|
Al Nisbet
Well
Said!
The Press
5 Dec 2013 |
 |
|
668 |
6 Dec 2013 |
Golden Homes |
Visit Golden
Homes to be told - it is back with Arrow to sort price out.
Email sent to all parties |
|
669 |
7 Dec 2013 |
Southern Response |
Our Files from Southern Response
finally arrive in 23 working days - Required within 20 working
days! |
|
671 |
9 Dec 2013 |
Meeting |
We have asked
for a meeting with all parties before Christmas,
Insurance\Project Manager\Builder\Lawyer\Ourselves |
|
672 |
10 Dec 2013 |
Arrow International |
FINALLY our case has been
escalated to top level for Arrow QS and Golden Homes QS to
sort out price. |
|
674 |
12 Dec 2013 |
|
No news yet |
|
680 |
18 Dec 2013 |
NO MEETING
we asked for! |
NO DECISION
from
TOP LEVEL of Arrow
and Golden Homes
so the wait goes on and on! |
|
693 |
|
|
SO
ENDS ANOTHER UNSATISFACTORY YEAR WITH LITTLE PROGRESS ! !
|
|
|
2014 |
YEAR 4 |
Welcome to
2014 |
|
699 |
6 Jan 2014 |
Project Manager |
Due back at work 6th Jan or so
last message before Christmas said - waited until Wed then rang
everyday until 14th and no reply, left messages as well -
nothing. |
|
708 |
15 Jan 2014 |
Southern Response |
Rang case
manager - yes your Project Manager is back I'll leave him a
message to ring. What a great start to the year!!!! |
|
709 |
16 Jan 2014 |
Southern Response/Arrow |
Still no word from Project
Manager, so rang case manager again, this time we got an answer
- the contract manager they are waiting on is on leave until
next Monday - so now we know - it took 10 days to find that out. |
|
772 |
29 Jan 2014 |
|
Lawyer
requested meeting of all parties Insurer, Project Manager,
Builder |
|
723 |
30 Jan 2014 |
Arrow International |
New Project Manager appointed |
|
|
31 Jan 2014 |
Arrow International |
Meet new
Project Manager -
finally acknowledgement that we have been let down and failed by
the system - things will
now move forward with promise of about 2 weeks to contract, 4
weeks to consent after finalizing the foundations, agreeing on
price and get working drawings. It will take16 weeks in consent
to demolition and then 26 weeks to rebuild |
|
|
6 Feb 2014 |
Southern Response |
Letter outlining our EQC
contribution required when the contract is signed |
|
730 |
7 Feb 2014 |
Arrow International |
New PM rang as promised said we
can expect our contract to sign next week, then consent and
expect build to begin 20 weeks after contract is signed. |
|
734 |
10 Feb 2014 |
Arrow International |
Contract
approved and ready to sign - quick visit to Golden Homes to
clarify details - it has been 9 months! |
|
741 |
17 Feb 2014 |
9 months |
from sign off of plans to
signing Contract - unbelievable! |
|
742 |
18 Feb 2014 |
Meeting all parties |
Contracts
Manager-Southern Response, Project Manager-Arrow International,
Golden Homes Rep, our Lawyer, ourselves meet at Southern
Response and signed the Contract.
4/6 weeks
for working drawings then to Consent |
|
749 |
25 Feb 2014 |
BNZ |
Paid EQC money to Southern
Response (required within 10 days of signing contract) |
|
752 |
28 Feb 2014 |
Demolition Meeting |
Meeting on
site Arrow Demolition Team and contractor, also Project Manger
for H & S briefing. |
|
755 |
3 Mar 2014 |
Golden Homes |
Final decision about Outside
Colours for house made and signed off today. |
|
769 |
17 Mar 2014 |
Golden Homes |
It is now 4
weeks since working drawings
were due - but no -
MORE DELAYS,
we can expect them in 8 weeks now! They state by
17 April. Patience wears
thin. Are we likely to be in our home by next Christmas? |
|
772 |
20 Mar 2014 |
Arrow / Golden Homes |
Confirmation from Project
Manager that Working Drawings will take another 4 weeks!!!
due to out sourcing - overload 8 Weeks in all! |
|
779 |
27 Mar 2014 |
Golden Homes |
Consent
Manager at Golden Homes made contact - sent copy of PIM |
|
780 |
28 Mar 2014 |
Golden Homes |
Obtained copy of plans - changes
agree to and signed as part of Building Consent not made to
bathroom. |
|
783 |
31 Mar 2014 |
Golden Homes |
Apologies and
missed changes now incorporated in plans. |
|
790 |
7 Apr 2014 |
Golden Homes |
Resource Consent granted -
needed because we are in Flood Management Area |
|
800 |
17 Apr 2014 |
Golden Homes |
It is now
800 Days
since we signed the agreement to Rebuild. Working drawings due today
but nothing!!! |
|
|
|
|
Easter Weekend followed by ANZAC
Day we lose another 10 days!
1,2,3,4,5,6,7,8,9,10.....days! |
|
811 |
28 Apr 2014 |
Golden Homes |
Finally
we go to CONSENT but not before one
last sting - the house had to moved 100mm to the west because
roof was too close to fence, until we pointed out fence was on
Right of Way - then they said it was OK. Maybe 6 to 8
Weeks....... |
|
813 |
30 Apr 2014 |
Arrow International |
Demolition date set as 23 June
2014 - Time to sort out Temporary Accommodation, book the
carrier. |
|
814 |
1 May 2014 |
Landlord |
Confirmed 2 bedroom apartment in
central city. |
|
814 |
1 May 2014 |
Trends Kitchens |
Meeting to discuss kitchen plans |
|
828 |
15 May 2014 |
Trends Kitchens |
Received plans via email - price
over 50% more than PC sum allocated. |
|
835 |
22 May 2014 |
Trends Kitchens |
Difficult to talk to. Contract
say Roxx benchtop (told similar price to TriStone) but were
quoted Laminate, soft close door and draws not included in price
but GH said we would get them. |
|
839 |
26 May 2014 |
Golden Homes |
Now 4 weeks since Consent went
in and
NO communication
from Golden Homes despite being promised regular updates. |
|
841 |
28 May 2014 |
Golden Homes |
Meeting with Project Manager and
GH to discuss Kitchen. |
|
842 |
29 May 2014 |
Golden Homes |
Consent is granted!
Just 29 days (4 weeks, 1 day)
that is great! We were told 8-16 weeks |
|
848 |
4 June 2014 |
Golden Homes |
Meet the Construction
Supervisor. Confirmed demolition date for 23 June 2014. |
|
856 |
12 Jun 2014 |
Trends Kitchens |
Kitchen plan is looking good |
|
863 |
19 Jun 2014 |
|
Move out today
- temporary accommodation for 30 weeks! that's 9 January - we
feel it will be Feb before we are back |
|
867 |
23 Jun 2014 |
|
Handover date
- beginning of demolition process -
so the next stage of the journey begins..
2 years 5 months since we signed contract to REBUILD 8th
February 2012!!!! |
|
870 |
26 Jun 2014 |
Trends Kitchens |
Another meeting re
kitchen - progress being made |
|
871 |
27 Jun 2014 |
Safe Power |
"Power Has Been
Removed" sticker on window |
|
874 |
30 Jul 2014 |
Mac
Developments |
House now fenced |
|
878 |
4 Jul 2014 |
Mac
Developments |
Garage door removed,
heat pump removed |
|
883 |
9 Jul 2014 |
Mac
Developments |
Doors and windows
removed |
|
888 |
14 Jul 2014 |
Mac
Developments |
Demolition Day
- kitchen removed, roof tiles removed, batts removed - then
DEMOLITION |
|
890 |
18 Jul 2014 |
Mac
Developments |
Section now cleared |
|
894 |
22 Jul 2014 |
Surveyors |
Set out new house today |
|
903 |
29 Jul 2014 |
Faulks |
Excavations for
foundations started today to depth of 500 mm below ground level |
|
908 |
3 Aug 2014 |
Faulks |
Back fill now
completed |
|
910 |
6 Aug 2014 |
Mr Box |
Foundations
started today and could take 4 weeks.
Mr Box fast, no fuss, start to
finish foundation solution that is 100% reusable boxing and
stake fastening system - good for environment. |
|
916 |
12 Aug 2014 |
Arrow |
Meeting with Project
Manager to sort out stalemate with kitchen progress |
|
916 |
12 Aug 2014 |
Firth Concrete |
Jacking slab of
concrete laid today |
|
918 |
14 Aug 2014 |
Trends Kitchens |
Signed off on
kitchen today |
|
918 |
14 Aug 2014 |
Mr Box |
Jack now
being attached to foundation |
|
920 |
16 Aug 2014 |
Mr Box |
Jacks completed,
more polythene and polystyrene laid as jigsaw continues. |
|
922 |
18 Aug 2014 |
Mr Box |
Polystyrene
completed, all plumbing pipes installed |
|
923 |
19 Aug 2014 |
Mr Box
|
Steel
springs surround the jacks which are bolted to jack slab,
polythene is placed between slabs to allow separation,
reinforcing steel is added. |
|
925 |
21 Aug 2014 |
Mr Box,
Devi Heating |
Rebates installed
ready for concrete pour, all inspected by engineer,
cables for under floor heating laid today! |
|
926 |
22 Aug 2014 |
Firth Concrete |
6 am Concrete pour
begins - drama only 2 of 3 zones of under floor heating
installed - concrete poured what can we do?
Solution from Devi
Heating to " Channel in" missing section. |
|
929 |
25 Aug 2014 |
Mr Box |
Boxing removed |
|
930 |
26 Aug 2014 |
Mr Box |
Foundations finished
- section cleared. |
|
931 |
27 Aug 2014 |
Hansen's |
Drain layers arrive. |
|
932 |
28 Aug 2014 |
Devi Heating |
Lounge area marked
for "Channel in" heating. |
|
933 |
29 Aug 2014 |
Hansen's |
Drain laying
completed - 2 obstructing trees removed. |
|
939 |
4 Sep 2014 |
Devi Heating |
Channel for lounge
heating pad cut |
|
950 |
15 Sep 2014 |
Devi Heating |
Element installed |
|
951 |
16 Sep 2014 |
Devi Heating |
Element sealed |
|
959 |
24 Sep 2014 |
Wall Framing |
Finally steel frames is being
erected - today walls |
|
960 |
25 Sep 2014 |
Roof Framing |
Roof framing |
|
968 |
3 Oct 2014 |
Fascia & Gutter |
Fascia & Gutter installed today
- this is the first colour of our new house |
|
979 |
14 Oct 2014 |
Roof |
Roof started - this is 10 day
behind schedule. Like colour, looking good. |
|
982 |
17 Oct 2014 |
Roof Finished |
Looking good! |
|
983 |
18 Oct 2014 |
Windows & Doors |
Waiting for windows due 10 Oct
now due 6 November another months delay! |
|
988 |
22 Oct 2014 |
Deck |
Our Builder agreed to build a
composite deck - great news |
|
1000 |
3 Nov 2014 |
Plumber |
Plumbing put in walls today |
|
1002 |
5 Nov 2014 |
Wilpower Electrical |
Meeting with electrician and
discussion on lights, power points etc |
|
1002 |
5 Nov 2014 |
Wrap |
Finally the house is becoming
enclosed. Spoke too soon see below
 |
|
1003 |
6 Nov 2014 |
Window Frames
by Bradnams |
Most window frames arrived today
- but no glass, rest by 12th - glazing by 18th Nov!! Suppliers
running out of materials - aluminum & glass.... |
|
1015 |
18 Nov 2014 |
Bradnams |
Unable to deliver balance of windows - lost steel for bay window
in transit. It is now week 10 and windows usually take 4 weeks -
run out of steel and glass!! |
|
1017 |
20 Nov 2014 |
Bradnams |
Delivery final door
and bay window but DISASTER
they drop window on delivery to the site and its a complete write off
SO another 2 weeks delay |
|
|
We are now
|
into week 22
since |
we moved out for a
30 week build with these delays its looking like 42 weeks-10
mths! |
|
1023 |
25 Nov 2014 |
|
Install battens for
outside cladding while we wait for windows to be glazed onsite. |
|
1024 |
26 Nov 2014 |
Trends |
Marked out Kitchen |
|
1025 |
27 Nov 2014 |
WilPower/ Bradmans |
Started wiring.
Back door in, a few windows glazed |
|
1026 |
28 Nov 2014 |
CCC |
Passed the flashing inspection
from CCC now outside cladding can begin |
|
1027 |
29 Nov 2014 |
|
Birds found nesting
in rafters
- glazing is taking soooo long. |
 |
|
|
1031 |
3 Dec 2014 |
Bradnams |
Replacement Bay window finally
in. Glazers arrived to deliver some glass |
|
1033 |
5 Dec 2014 |
Wilpower |
Wiring has started.
Glazing almost completed, bay window board up to allow batts to
start. |
|
1034 |
6 Dec 2014 |
Cladding |
Finally the cladding
is put on in just one day. |
|
1036 |
8 Dec 2014 |
Batts |
Ceiling batts going in today |
|
1037 |
9 Dec 2014 |
Garage Door |
Garage Door installed, batts
completed - house is now closed in........................ |
|
1038 |
10 Dec 2014 |
CCC |
Pre line inspection passed. Gib
fixing and stopping scheduled for next week. |
|
1045 |
17 Dec 2014 |
Gib Fixers |
Gib Board going up
today |
|
1046 |
18 Dec 2014 |
Gib Fixers |
Gib Board finished - next a
council inspection in the New Year |
|
1052 |
24 Dec 2014 |
4.0 Magnitude
7:43
pm |
Christmas Eve we are
rocked by 2 quakes 2nd 3.3 magnitude at 8:43 pm how the memories
come flooding back! |
|
|
2014
|
 |
The year of SNAIL PROGRESS
but nevertheless progress.............. |
|
|
2015 |
YEAR 5 |
Welcome to
2015 |
|
|
6 Jan 2015 |
Gib Stoppers |
Inside is being prepared for
painting |
|
|
12 Jan 2015 |
Plasters |
Outside cladding is being
prepared for painting |
|
|
20 Jan 2015 |
Internal Doors |
Internal doors have been hung but glass panel doors are not
as ordered |
|
|
20 Jan 2015 |
Inside painters |
With windows sealed with plastic
can see little |
|
|
23 Jan 2015 |
Outside paint |
At last we can see the chosen
colour - it was so long ago had forgotten what it looked like. |
|
|
27 Jan 2015 |
Plasters finished |
Yes outside is looking good -
clean and crisp. |
|
|
28 Jan 2015 |
New Style Blinds |
Curtains measure - we managed to get
a brief look inside |
|
|
28 Jan 2015 |
Vanities |
Vanities are now installed |
|
|
29 Jan 2015 |
Ground Work |
Concrete measure design and shape |
|
|
29 Jan 2015 |
Designer Dirt |
Decide on 2 smaller decks and
front lawn |
|
|
4 Feb 2015 |
Site Meeting |
Golden Homes Project Manager,
Arrow Project Manager, Ground Work, Designer Dirt and us to
discuss ground levels and general layout. We felt levels were
all wrong and the house was below original ground level in back
corner. We were assured it would all work out. |
|
|
4 Feb 2015 |
Trends |
Kitchen arrived and assembly
began |
|
|
4 Feb 2015 |
Tiler |
Tiles being put around bath and then splashback in kitchen |
|
|
5 Feb 2015 |
Showers |
Showers installed and vitroglaze
applied |
|
|
12 Feb 2015 |
Fences |
Perimeter
fences have gone in preparation for driveway and paths |
|
|
12 Feb 2015 |
Planking |
Planking is down in foyer,
living and dining room |
|
|
12 Feb 2015 |
Kitchen |
Kitchen is
almost complete, bathroom tiles & Kitchen tiling done, lights
being installed, ensuite heating and tiles in. |
|
|
13 Feb 2015 |
Carpet |
Carpet is being laid today, not
happy because electrician and plumber are not finished and drive
and paths not in. |
|
|
13 Feb 2015 |
Letterbox |
They agreed to
replace our damaged letterbox |
|
|
13 Feb 2015 |
Finally a date |
We have been out of our house
35 weeks now and
finally we are given a tentative date for handover - just
another 35 days
on 20th March 2015 |
|
|
18 Feb 2015 |
Designer Dirt |
Excavations
for deck |
|
|
19 Feb 2015 |
Designer Dirt |
Deck base is down today |
|
|
23 Feb 2015 |
Designer Dirt |
Composite
Timber Decking by Gracol - eco decking. |
|
|
24 Feb 2015 |
HomePlus |
Wardrobe fittings installed |
|
|
25 Feb 2015 |
Ground Work |
Paths and
drive due to start today but 7 days delay ahead! |
|
|
26 Feb 2015 |
WilPower |
Air Conditioning unit install |
|
|
3 Mar 2015 |
Ground Work |
Excavation for
concrete starts |
|
|
4 Mar 2015 |
Arrow International |
Walk through with our Project
Manager - this is the first time we have been allowed inside the
house - Golden Homes quoted Health and Safety Regulations. |
|
|
5 Mar 2015 |
Ground Work |
Boxing going
in for paths and driveway |
|
|
10 Mar 2015 |
Cleaners |
House professional cleaned on
inside - does make a difference from our last inspection. |
|
|
11 Mar 2015 |
CCC |
Compliance
granted |
|
|
12 Mar 2015 |
Golden Homes
Arrow International |
Official walk
through after which Certificate of Practical Completion was
issued |
|
|
12 Mar 2015 |
Carters |
Finally internal
glass panel doors arrive - GH ordered correct doors, Carters
delivered wrong ones - took 51 days - still need painting and
hardware........... |
|
|
13 Mar 2015 |
WilPopwer |
Alarm & TV aerial installed |
|
|
14 Mar 2015 |
Ground Work |
Half concrete poured
- around the back and side was - concrete level with decks
- this is disappointing because the house was dropped 500
mm in ground when specs said 300 mm in ground and 300 mm above
ground. Something we will have to live with. Paths are
above foundation level in many places and only gained compliance
because they are 400mm out from building. |
|
|
15 Mar 2015 |
Cyclone Pam |
Spent many anxious days wondering if this will delay final
concrete pour tomorrow, just 5 days before handover. All
accommodations payments cease at handover, even if the drive and
paths are not in place. I do not want to move in before drive is
down. |
|
|
17 Mar 2015 |
Ground Work |
Final half of
concrete poured today - what a relief with just 3 days until
handover. |
|
|
18 Mar 2015 |
Painter |
Internal glass doors being painted also window seat, around
garage door. |
|
|
20 Mar 2015 |
Handover Day |
What do I say -
it was unreal - nothing like we imagined- GH & Arrow PM went
through the motions of handover - with so much unfinished -
even the garage door opener had not been installed, so many
things we had asked for not done.
An hour later we had garage door opener fitted, then the letter
box was installed, plastering under doors and windows completed,
but not painted. The curtains and blinds were installed. Waited
all day 8 hrs for Spark, (Chorus) only to be told everyone had gone home.
Did we feel the house was ours - not really......... |
|
|
21 Mar 2015 |
Chorus |
Spark (Chorus) finally turned up at 8.30 am - just one day late announced
phone was connect but we had no dial tone and no data. New data
sockets - had to borrow an adaptor from neighbour and finally
got phone working - needed to get electrician back to sort out
data. |
|
|
22 Mar 2015 |
|
Where to start - the
outside was supposed to be cleaned, the Air Con unit had been
filled with soil during shaping of paths, we expected it to be
cleaned but no. |
|
|
23 Mar 2015 |
Roofer |
Downpipes installed, disappointing that each pipe left 4 holes
in plaster from temp pipes installed for concrete to be poured. |
|
|
24 Mar 2015 |
Wilpower Electrical |
Finally had data and
phone lines sorted, just need computer to set up broadband,
technology is changing and no one explained changes to switches
and adaptors to make things work. |
|
|
25 Mar 2015 |
Meridian |
Downpipe screw holes now plastered over. Had to order Night 'n'
Day metre from Meridian, what we previously had but builder use
Contact Energy and the installed Economy 24 metre. - Is nothing
straight forward? we built like for like and installed under
floor heating which needs Night'n'Day metre. |
|
|
26 Mar 2015 |
Conroy |
We move in today. Early start 8 am we
moved out of flat with our basic possessions. Concrete still
drying. Now we had no TV reception. |
|
|
27 Mar 2015 |
Wilpower Electrical
Chorus |
New aerial cable needed to establish reception.
Late again due 8-12 noon arrived 2:30 installed VSDL and removed
crackle from phone line. |
|
|
30 Mar 2015 |
Conroy's |
Our stored Furniture is
back today. Finally today we got
our Container from storage exactly 40 weeks later just 10 weeks
more than we were told. we now have everything in one places
again feels good except the car, we are still waiting for
concrete as instructed. |
|
|
2 Apr 2015 |
Concrete |
Concrete has been down 2 weeks now so finally able to put car in
garage. |
|
|
10 Apr 2015 |
CCC |
Code of Compliance
issued today - so that
completes a major part of the Rebuild. |
|
|
24 Apr 2015 |
Designer Dirt |
Lawn was laid in the front - looking good |
|
|
28 Apr 2015 |
City Care |
No access to
property during day for the last week, while curb and
channeling is being replaced, we hope to have concrete in today. |
|
|
3 Jun 2015 |
Lounge Window |
Lounge window replaced 3 imperfections in the glass |
|
|
9 Jun 2015 |
Road Closed |
The Road is finally open for the first time since we moved back
- what a relief! |
|
|
18 Jun 2015 |
Maintenance Period |
It is 3 months since
we moved in and Maintenance List has been sent to Golden Homes.
Generally minor in nature. |
|
|
19 Jun 2015 |
Golden Homes |
GH
Project Manager visited and fixed may of smaller problems,
followed by several tradesman over next week. We now have 1/3 of
problems resolved. |
|
|
14 Jul 2015 |
Golden Homes |
Email saying most
items take 4 to 6 weeks - well that took 5 months to complete |
|
|
25 Nov 2015 |
Everyone |
The final things on our Maintenance List were completed.
Now the house is really ours! |
|
|
|
|
|